Stowe Country Club Update

General
The weather was once again the biggest challenge over the past month. The month of June brought over ten inches of rain to Stowe Country Club. In May, we battled the extreme lack of rain and now June was the complete opposite with record setting rain totals. This "new normal" of extreme weather patterns is reality and how we prepare to overcome these challenges is the difference between success and failure. The heavy rains were a good test for the new fairway and bunker drainage. These new drainage projects performed very good and we will continue to address other wet areas by installing more drainage.
Squeegeeing greens before Kirkwood Tournament

Kirkwood week was a challenge due to the rain. The days leading up to the event brought significant rainfall. The crew spent all day Wednesday before the tournament squeegeeing water off greens. Our sixth and final round of pushing water came as the sun went down. These efforts allowed for firmer greens for the first three days of the event. While Sunday ended in a rain-out, I am very proud of our crew's effort in preparing for the tournament.

Greens
The winterkill spots have grown in very well. The repair would have been much quicker if it was not for the excessive rain in June. These areas were damaged in the winter due to the fact that they puddle with water and then freeze. The nature of these areas to puddle made it difficult for the seed to establish because of being submerged under water and being constantly washed away. As the Kirkwood tournament approached the excessive squeegeeing damaged some of the seedlings setting the recovery back even farther. Mark Finch, golf course superintendent, did a superb job with the re-establishment of these areas. Mark worked diligently on a day to day and hour by hour basis for two months to get these damaged areas back to full turf coverage. Growing in turf on established golf greens is very difficult due to the ongoing maintenance of the surrounding turf and golfer traffic.
Root pruning at 15 tee

Tees
There were some recent changes to the fifteenth tee. The granite tee marker and bench were moved to make room for a root pruning operation. The close proximity of this tee box to the row of white pines negatively impacts the turf quality due to shade, needle shed, and root intrusion. The shallow rooting of white pines steals water and nutrients that is needed by the turf. Root pruning cuts the tree roots before they intrude into the teeing ground. We use the drainage trencher that was purchased last year to shear the roots. This process is an annual maintenance activity that will help the fifteenth tee recover faster from divoting and wear.


Fairways
The big push on fairways has been to achieve one hundred percent full turf coverage. The crew has been diligently seeding and sodding thin areas. Most of the damage is from poor drainage. Low areas on three, five, and twelve have had chronic thin areas. This is unacceptable for myself and staff. We will continue to sod and reseed until we reach full turf coverage in fairways.
Construction of cart path on 4th hole. Notice old path routing
to the left of new mounding.

Projects
The revitalization of the fourth hole is nearly complete. Multiple issues impacting the quality of this par three have been addressed. The over planting of trees on the left and right side of the hole blocked the view of the entire green complex and limited the use of the teeing ground due to blocked shots. A dozen trees were removed over the past two winters opening up the view of the green with surrounding mountain ridge line and providing full use of the tee. The fescue grasses that existed under the trees have come back to life and now provide a stunning framework to this hole. The cart path running along the right side was damaged in multiple sections, was too narrow for maintenance vehicles, and was positioned in a way that impacted the look of the hole. The path was repositioned and is now hidden from view. Slight mounding was added to aid in blocking the view of the cart path. Fescue was then planted along the new path to add additional screening of the path. As the fescue grass matures on both sides of the hole it will provide a stunning look to this great par three. The path is scheduled to be paved this week. Finally, the bunkers have been aggressively edged to bring back the original shape and add a better visual from the tee box. New sand was then added to provide consistent shot making.

The Spring Hustle


   As May has come to a close, it is a good time to review the condition of the golf courses and discuss the projects that have occurred. The variability of the Vermont spring is always a challenge for golf course maintenance. While planning operations is essential, it is even more important to be able to react quickly to unexpected challenges.

    The biggest challenge this spring has been the dry weather. While recent rains have helped, early spring rain did not occur. The successful start up and operation of  both irrigation systems has been of extreme importance. As the turf completes its winter dormancy and begins to grow, the need for water is crucial to initiate growth. While it might be hard to believe, early irrigation in May is crucial for positive turf growth. Turf is grown in sand based systems that can lose moisture quickly. In addition, the closely mown turf is very susceptible to moisture loss. Compounding the challenge of irrigating in a dry spring, a deep frost layer caused an above average number of breaks in the irrigation system piping. The turf care teams have been hustling to repair these breaks so that irrigation can continue.

9th green at Stowe Country Club. Notice standing water in the
damaged areas.
    Stowe Mountain Club (SMC) and Stowe Country Club (SCC) courses were impacted by winterkill this spring. The two reasons for winterkill this year were crown hydration and wind desiccation.  Stowe Mountain Club received desiccation damage on the first tee and sixth green. Those two areas were impacted due to the exposure to the severe north winds in the winter. In my eleven years at Stowe Mountain Club, I have never seen these levels of wind desiccation damage. The damage occurs due to the severe winds simply drying out the above ground tissue of the turf. Most often the turf can withstand the winter winds, this year the extended cold weather coupled with high winds pushed the turf to the extreme limit.

    This spring both courses were impacted by crown hydration. Ideal turf growing conditions during spring thaw requires sufficient surface drainage preventing standing water. Crown hydration occurs when night time temperatures drop below freezing. The cells in the turf plant will explode due to the freezing standing water. The common theme with this type of damage occurs in chronic wet areas. Stowe Country Club experienced crown hydration on the greens of one, nine, thirteen, and eighteen. At Stowe Mountain Club the damage occurred in the low lying areas of the fairways. The worst of the damage at SMC was found on eight and twelve. The turf care teams have seeded the damaged areas and positive germination has occurred. Full coverage is expected by the end of June. In reviewing the best options for damage prevention in the future, the installation of sub surface drainage to these wet areas will significantly reduce the potential for crown hydration.

    Currently, the Stowe Mountain Club crew is wrapping up a couple drainage projects that were initiated in the late Fall of 2014. The hillside on the eleventh hole had drainage installed to firm up the slope due to springs emerging through the turf. These springs were captured and piped through the fairway. The fourteenth fairway had drainage installed to help prevent winter damage and help firm up the fairway after rain events. These projects are in the final stages of completion.

    At Stowe Country Club a large key culvert was replaced in the practice field. The old pipe was made of metal and was rusted out creating multiple sinkholes holes in the field. Coupled with this project is the addition of target greens in the practice field. When completed there will be four greens for players to hit at. These greens will replace the current poles. The design of these target greens is such that they are raised slightly above the field and the top surface will be mowed at a short height. This raised angle and low cut will provide a larger target for players to aim at and improve their game. Two of the four greens have been shaped and seeded. the other two are still under construction. As an added visual aesthetic, there will be pseudo bunkers placed in front of these greens. These features will look like bunkers but will be built in such a manner that mowing and picking balls will not be extra maintenance.

Wash pad at Stowe Country Club. Notice grass clipping
separation system in trough.
    Finally, a project was completed at the SCC maintenance facility that has revolutionized how the turf care team  conducts business on a daily basis. A new equipment wash pad was constructed away from the fourteenth tee box. Prior to this new wash area, all equipment was washed directly adjacent to the tee box. The subsequent activity and smell of decaying grass clipping significantly impacted the golfing experience. The new location is on the other side of the road out of site of the public and golfers. The construction of the wash area is such that grass clippings can be managed properly reducing the odor and the water runoff is treated using a natural buffering system. Maintaining great golfing conditions starts with effective, efficient, and safe working conditions at the maintenance facility.

    While the dry May weather has presented some challenges for the grounds staff, the dry firm conditions have been excellent for golf. I hope everyone has had the opportunity to get out and play. Our two golf courses are very close to rebounding from winter and will soon be in top form. Thank you for your patience and assistance while we continue to maintain and improve the golfing experience at Stowe Mountain Resort.

A Short Look Back and a Long Look Forward

The 2014 Golf Season was defined by the epic level of turf injury that occurred from the severe winter weather of the "Polar Vortex". Widespread turf loss was reported throughout the Northeast and Canada. Unfortunately, six greens at each of Stowe's courses experienced some type of turf loss. The areas that experienced the most damage were greens seven and thirteen at Stowe Mountain Club (SMC) and twelve and thirteen at Stowe Country Club (SCC). Fairway damage was also significant at each course. While many golf courses suffered for months with visible damage it was hard to find any damage on either of Stowe's courses by late June. The hard work and diligence of both crews  is commendable.

Late Fall of 2014 was a productive time at SCC with focus on drainage, infrastructure repair, and tree management. Most projects on the to-do list were completed with exception being the repair to the green-side bunker on the ninth hole. Completed was the repair to the bunker on one green and the fairway bunker on eighteen. Good sand and new drainage were installed, and the bunkers will play and look better in any type of weather. The re-contouring of the bunker on eighteen provides an important architectural feature-the hazard is now visible from the tee.

Re-contouring SCC 18 Fairway Bunker
Last season a tremendous amount of work went into improving the drainage at both courses. "Slit drainage" was installed in multiple areas. Slit drainage utilizes a unique two inch pipe that is back filled with straight sand. This design has proven its success on our clay based soils. The fairway drainage on nine and eighteen will now allow for firmer playing conditions especially during extended wet periods.
  
Installing Drainage SMC 14 Fairway
The unique location of the SMC course provides a challenge for turf survival due to the length and intensity of the winter weather. We are continually developing new methods and practices to prevent winter kill. Keeping the playing surfaces free of standing water is paramount to good in-season playing conditions and winter survival. At the SMC course, fairway drainage work was initiated on eleven, fourteen, and fifteen. Many of the new drainage lines were left open for the winter to assist in water movement during the spring thaw. These areas will be recovered before opening day. 

This winter we have been busy with the continued implementation of the SCC tree management program. For more information and to review this program, read the blog posted on 5/11/14. As it was last year, the focus this winter is on damaged trees that pose a safety hazard and trees that are overgrown and impacting play and the aesthetic of the course.

Golf is a game of options. Many of the trees found next to teeing grounds force the player to play only one type of shot. Opening up the tee shot to multiple options is a sign of a well designed golf course. For example, two white pines were recently removed from the ninth tee. These two white pines forced play to the left from the white and blue tee box. From the back tee, the tee shot was exceptionally narrow due to the overgrown canopy. Players now have the option to draw or fade the ball into the landing area. The next trees to be removed will be the white pines behind the sixteenth green. These four trees have been damaged by the violent storms that have rolled through the area in the past decade. The interior of the trees have signs of rot and are deemed hazardous. 

White Pine behind SCC 16 green with severe
structural damage and rot
From an architectural perspective the number sixteen green sits atop a beautiful rise that provides a panoramic view. It is a common misnomer that all golf greens need some type of backdrop for the purposes of "framing". While in some cases a frame provides focus and depth, in others an open sight-line behind a green can also provides an exciting challenge for golfers. In researching the course history the architect, William F. Mitchell, did not intend for this particular green complex to have a backdrop of trees. As a result, no replacement plan is in place once these damaged trees are cleared.

The Stowe Golf Agronomic Team is excited for the upcoming 2015 golf season and we hope the winter weather is as good to the golf courses as it has been to the skiers and riders. While we continue to enjoy the winter season, we will continue working hard at both Stowe Country Club and Stowe Mountain Club. 

A Work In Progress

    Golf courses are in a perpetual state of decline. It is no different from any other manmade object. A house, a car, or a road will eventually need some type of maintenance activity to keep it performing and looking good. Additionally, due to the fact that golf courses are a living and breathing (respiring actually) thing they can also be compared to human health. When neglected, the body and mind will decline at a faster rate than one that has had preventive health care and proper nutrition. Providing the golf course with proper nutrition, preventive treatments to ward off pests, removal of excess thatch, repair of failed infrastructure, and proper tree management ensures its long term health.
    While the term "a work in progress" often refers to a situation that needs work to become good, in the golf course world, it refers to the concept that the act of continual work is paramount to the future health and playability of the course. The simplest example of such work is aeration. The Mountain and Village course greens are two to three weeks out from a hollow core aeration. While the greens are a bit bumpy in the immediate days following aeration it is the long term health and performance of the greens that need focus. The removal of thatch and organic matter through hollow core aeration prevents soft greens that footprint easily and become bumpy, stay wet for extended periods, are more prone to disease, and become more susceptible to winter injury.
   The more complex work is the revitalization and repair of golf course features. Such work includes drainage repair and installation, repairing damaged cart paths, tee top leveling, re-contouring of bunker edges, and tree work. Some of this work occurred this Spring while other work will occur this Fall.

Stowe Mountain Club
  • Continued aeration. Fairway aeration is ongoing. We are currently half way through this process. With
    Fairway aeration and clean up
    good weather this process will be complete by next week. Tees and approaches will follow and only take a couple days to complete.
  • Drainage on the right side of eleven fairway. This hillside is crucial to the playability of this hole. Tee shots that hit the hill stand a good chance of rolling back to the fairway. Due to some groundwater springs, this hillside is often soft and impedes the ball from rolling to the fairway. 
  • Extend drainage in fourteen fairway. Last Fall, a main drain line was installed near the landing area. The main purpose of this line is to alleviate chronic winterkill caused by excessive wet turf during snow melt. The installation of this drain line was successful in limiting the amount of winterkill this Spring. This line will be extended and laterals will be installed to further eliminate the potential for winterkill.
  • Fairway drainage on fifteen fairway. As with fourteen, this fairway succumbs to winterkill due to wet conditions during snow melt. Drainage will be installed to assist with winter survival.
  • An ongoing project is the repair of a ground water spring above the first landing area on the eighth fairway. Due to the proximity to the dam, this project has been a slow and deliberate process. The design to alleviate this chronic wet spot has been highly engineered and managed. A subcontractor is currently being secured to finish the project. 
  • New forward tees have been built on the third hole and eighth hole. The third hole tee is now open. The eighth tee was constructed from the spoils of the previously discussed wet spot on eight. This tee has been seeded and will open Spring of 2015. 
  • Fescue has been planted along the stone collar on the ninth hole.

    Collar extension on #9
    This work also used the spoils from the drainage project on the eighth hole. Planting fescue along the edge of Peregrine Lake softens the look of the stone and allows for additional playability to mis-hit tee shots.  
  • The collar on the right side of the ninth hole has been extended. This collar extension was done to aid in the approach shot bouncing to the left and landing on the green. Collar extensions similar to this work have been installed on the sixth, eighth, eleventh, and thirteenth. These creeping bentgrass collar extensions are done to assist with better playability around the greens. 
Stowe Country Club
  • Tee aeration is complete. Fairways and approaches will be aerated after Stowe Mountain Club is complete. All of the aeration equipment is shared between both courses. Aeration at Stowe Country Club is very important because of the heavy clay soils that exist under all the features. Alleviating soil compaction and increasing surface drainage is part of the ongoing work that promotes healthy turf and good playability in all weather conditions.
  • A new culvert pipe was installed at the practice facility field. This pipe transfers water from a stream that enters the field on the west side. The existing pipe was an old metal pipe that had completely rusted and caved in. Prior to the installation of the new pipe being, water would flow onto the field and pool up for extended periods of time.
  • A new culvert pipe was installed on the thirteenth hole. This pipe had completely failed like the one on
    Silted bunker on #13
    the practice field. During the Winter melt, the pipe collapsed and silted in the greenside bunker. The pipe was replaced and the bunker was also repaired. New drainage was installed in the bunker along with all new sand being added. 
  • New forward tees have been constructed on the sixth and ninth holes. The ninth tee opened recently and the sixth tee may open in a few weeks if the weather provides good growing conditions. 
  • The final step in drying up the seventh hole was completed this Spring. The wetland to the left of the landing area was leaching water through the soil creating chronic wetness in the fairway. An interceptor drain was installed to divert this water away from the fairway. 
    Repaired #13 bunker with drainage
  • The new upper practice tee was opened during Kirkwood week. We doubled the size of the tee surface, moved the ball machine away from the road, eliminated a small practice green and bunker that had gone into disrepair, and provides a new staging area for carts during tournaments and outings.
  • This Fall, we plan on repairing multiple bunkers and fairways. These projects will commence immediately. The order of completion is as listed below.  
    • Multiple laterals will be installed on the eighteenth fairway. This work was started last Fall by installing a drainage mainline. We will connect multiple laterals to this mainline in the coming weeks.
    • The fairway bunker on the right of eighteen will be re-contoured and drainage will be installed. This bunker has grown in over the years and pools up after rain events.
    • A mulch bed will be installed underneath the spruce grove on the left of eighteenth hole. This work will be done to provide definition to the landing area and to protect the future health of these trees.
    • The greenside bunker on the first hole will be repaired. Currently, water leaches out of the bunker and settles near the approach. This area has turned into a chronic wet area that is very difficult to play out of. Additionally, the general appearance of this area is very poor and should be corrected because it sets the tone for the entire golf course. Internal drainage in the bunker will be installed to transfer the water away from the playing area and new sand will be added.
    • The second half of the ninth fairway will be drained and the greenside bunker will be repaired. This fairway does not drain after rain events. A main line will be installed with multiple laterals. The bunker will be re-contoured to divert surface drainage away from entering the bunker, internal drainage will be installed, and new sand will be added. 
    All of this work is being done with an eye on the future. The short term disruption to play is done for the long term goal of the continued enjoyment of both golf courses by the members and players. This continued enjoyment is based soundly on the hard work of the maintenance team and the commitment of Stowe Mountain Resort to provide great conditions.  We thank you for your patience and understanding while all of this work is in progress. 

 

Fescue Revitilization Project

    Approximately ten years ago Stowe Country Club created a plan to stop mowing selected rough areas to reduce operational costs associated with mowing. These areas were previously mowed at the rough height of 2.5 inches. The savings were created by less fuel from the reduced acreage and in the reduction of man hours it took to mow. Additionally, there was less wear on the mowing equipment. A second aspect of this plan was to add a new aesthetic to the golf holes. 
    This new aesthetic aspect for the golf course is where the plan fell short. While the idea was good, the execution lacked follow through. As time progressed, the high rough areas were overrun with field grasses and weeds which resembled an unkempt pasture. From a golfing aspect, finding a golf ball in the weeds and thick pasture grass was almost impossible. The other negative aspect is that the look of weedy high grass areas presented the impression of neglect. Playing a golf course that has clean visual lines is a pleasant and inspirational experience. The opposite feels chaotic and distracting. 
    Earlier this year, a plan was initiated to revitalize these high grass areas to add a positive aesthetic to the course in addition to making them more playable. The plan is centered to promote the growth and establishment of fescue grasses. Fescue is a thin bladed grass that predominates on golf courses throughout Scotland, England, Ireland, and Wales. In these regions, fescue is a definitive characteristic of a links golf course. The actual playing surfaces, greens, tees, and fairways, are fescue on these European courses. However, the true charm and beauty of a links course is the un-mown fescue that surrounds a golf hole. The wispy seed stalks of fescue that turn a golden brown starting in mid-summer create the true beauty of a links course. Of course, fescue is not just on links courses. Many golf courses, wherever the region, have fescue in the outer rough areas to provide that beautiful flowing golden look.  The 2015 US Open will be played at Chambers Bay in Washington. This golf course is built on an abandoned quarry and was planted to fescue. Greens, tees, fairways, and rough are pure fescue stands. From it's inception, Stowe Mountain Club focused on maintaining expansive stands of fescue that frame many of the golf holes. The aesthetic created by the fescue during this time of year is beautiful. Besides the aesthetics, the other important aspect of fescue is the ease to find your golf ball and to successfully advance it. This is accomplished by planting fescue on low quality soil, never irrigating, and never fertilizing the grass. The thinner the better. 
Elimination of non-desirable grass surrounding thriving fescue
Between the 6th green and 7th tee
    The challenge at Stowe Country Club is that the fescue areas are overgrown with weeds and non-fescue grass and the soil has high water retention and nutrient holding capacity. Elimination of the weeds and field grasses is being executed with products that will eliminate all the undesirable plants but the fescue. Multiple applications are needed since many weeds and non-fescue grasses can be very persistent. Multiple mowing is another aspect of the revitalization of the fescue. Multiple mowing throughout the year will eliminate the ability for weeds to seed out, and will cause the depletion of the carbohydrate reserve of the plant that will eventually lead to the plants decline. The mowing will conversely help the fescue thrive and spread. Check out the recent USGA article on this topic. USGA ARTICLE
    This process takes time. Expansive stands of fescue at Stowe Country Club will take three to five years. As these areas are denuded of undesirable plants, new fescue will be sown. Maturation of fescue after establishment is slow taking three to four years. We appreciate your patience during this conversion. The end product will be worth the time and effort. Once established, the fescue will provide a beautiful aesthetic to a round of golf and it may even lower your score. For more information on fescue, visit a prior blog titled "Fescue".

Bentgrass

Bentgrass is the preferred turfgrass on fairways and greens in the northeast. The ability to tolerate low cutting heights, aggresive lateral growth habit, dense canopy, and stress tolerance make it a suitable playing surface for the game of golf. The predominant species of bentgrass is creeping bentgrass. Within this species there are hundreds of cultivars. The breeding of creeping bentgrass is a very competitive business due to the golf course industry. The other type of bentgrass is velvet bentgrass. This bentgrass had its hayday in the 1950's and 60's on golf courses. It is an old variety of bentgrass and existed before many creeping bentgrasses were bred for golf turf. Since that time creeping bentgrass has surpassed velvet bentgrass as the preferred golf course turf.
Graden cultivation
We manage both courses in a manner that promotes bentgrass. We do not simply grow "grass". Our mission is to promote bentgrass growth and overtime increases its population on greens and fairways. Stowe Mountain Club has A4 creeping bentgrass on the greens and L93 creeping bentgrass on the fairways. These two grasses were chosen by Billy Fuller from Bob Cupp Design, the golf course architect. Billy was the Agronomist for Bob Cupp during the construction of the course. The interesting story behind A4 is that Billy worked with Dr. Joe Duitch from Penn State to breed this specific cultivar. While the superintendent at Augusta National in the early 1980's, Billy showed Dr. Duitch a patch of bentgrass on the par 3 course that exhibited a very tight and smooth growth habit. From that patch the A4 bentgrass was bred to be what it is today. It is one of the premier bentgrasses for putting greens in the world. The "A" stands for Augusta. The L93 bentgrass in the fairways is also a newer cultivar. It is considered a workhorse in the golf industry. It is a very versatile turf that can also be used for tees and greens. The tees at the Mountain Course are not bentgrass but rather a blend of chewing fescue and dwarf Kentucky bluegrass.
Core aeration cultivation
Stowe Country Club has a much more diverse mix of turf species. The greens are a mixture creeping bentgrass, velvet bentgrass, and annual bluegrass. Many of you know annual bluegrasss by its scientific name, Poa annua. This mixture of grasses creates a very challenging scenario for reaching the goal of smoothness. You can identify velvet bentgrass by it's very fine leaf blade, dense growth habit (looks like moss) and it's soft puffy feeling under foot. It is also visible on the greens due to its round patchy growth. In between these velvet patches is Penncross creeping bentgrass. Unlike A4 and L93, Penncross is a very old cultivar. In fact, it is considered one of the first cultivars of creeping bentgrass. Pencross has been around for many decades and can still be purchased to this day. Pencross is known for its aggressive creeping or lateral growth habit. This can be viewed as a positive aspect due to its ability to creep laterally to fill in any damaged area or divot. However, on greens it is a negative attribute because it produces very long leaf blades that makes for slower and grainy greens.

In The History of Stowe Country Club author Lynn Altadonna, explained that the greens were sodded to velvet bentgrass when the 18 hole course was built in 1962/63. The sod came from a defunct golf course called Kearsarge Golf Club in New Hampshire. The Village Course architect, William Mitchell, was known throughout New England for using and promoting the use of velvet bentgrass. There is no doubt that he had a role in this procurement of sod. The problem with sodding greens, especially velvet, as opposed to seeding greens is the existing thatch layer. Thatch is the layer of old stem material that builds up below the turf surface. Bentgrasses as a whole are prolific thatch producers. While thatch is simply the by-product of producing quality playing surfaces, proper thatch management of is the difference between good and bad turf. The basis of proper thatch management is to mechanically remove the thatch through core aeration and vertical mowing. The USGA recommends the removal of 15-20% of thatch surface annually for quality playing surfaces. This chart explains how to get to those percentages Surface Impact. The strategy at Stowe Country Club is to complete two 1/2 inch core aerations at 1 x 2 inch spacing with an additional Graden verticut. All three methods of cultivation equate to an 18% surface impact. At Stowe Mountain Club a less aggressive management is effective due to the young age of the greens to where the frequency of aerification will impact 10% of the surface.

As stated earlier, velvet bentgrass has fallen out of favor in the golf course industry. The main reason for this is that it is the most prolific thatch producer out of all the cool season grasses. If aggressive aeration and vertical mowing is not done on a regular basis the velvet will become puffy, bumpy, and play poorly. Since velvet at Stowe Country Club was initially installed and was not aggressively cultivated over the years, it has aggressively produced a determinate layer of thatch. Moving forward, proper agronomic practices will be initiated such as aggressive aeration and verticutting to regain the quality of the putting surface. In addition to controlling thatch levels, the cultivation of the greens will assist in conditioning the Penncross to be much smoother and less grainy.

It is our goal at Stowe Golf to produce excellent playing conditions through the production of quality bentgrass. Thank you for your patience during these periodic maintenance procedures to restore the turf. We hope that players will appreciate the  high quality playing surfaces that will grow in based on sound management practices.

Stowe Country Club Trees

The following bullet points are the foundation of our tree management program at Stowe Country Club. The strategy is to keep maintenance costs down, maintain good turf quality, maintain healthy trees, create and maintain the wonderful vistas, and eliminate obstructed tee shots.
  • Tree plantings predominated by white pine, red pine, and spruce trees (all conifers).
  • These trees were used due to their cheap cost and quick growth.
  • The over reliance of pine and spruce species has lead to an increase in disease potential. Many trees are showing damage from Diplodia blight.
  • A more diversified tree population reduces concerns of catastrophic tree loss due to pathogens or insect pests.
  • Where existing tree stands provide crucial strategic importance or screens, a diversified tree replacement program will be considered using deciduous species.
  • Pine and spruce trees create a large amount of ground litter from branch, cone and needle shedding. This leads to direct maintenance costs due to the need to remove such litter for playability. Removal of certain trees will keep maintenance costs down.
  • Root extrusion from soil surface has caused a major playability and safety issue.
  • The most effective and sustainable way to maintain trees next to golf turf is to create mulch beds. These beds will hide tree litter and cover exposed roots. High priority tree beds will be identified and maintained.
  • Current maintenance program is to trim the grass below trees. This requires many man hours. Installation of tree beds will assist in keeping maintenance costs down.
  • Absence of tree beds has negatively impacted health of trees due to lack of soil nutrients available.
  • Conifers grown in open or “pasture” settings produce prolific branching. This branching weakens over time and is prone to failure when impacted by wind or ice storms. This loss of limbs after storm events creates excessive maintenance costs due to cleanup.
  • Trees and golf course turf do not coexist very well due to the competition for water and nutrients.
  • Trees use more water than turf. This leads to browned out turf on the edges of golf holes in midsummer due to trees out-competing turf for water. Our current center row irrigation does not provide sufficient irrigation to the edges of golf holes to help the turf compete with the trees for water.
  • Coniferous trees are shallow rooted. This shallow rooting disrupts the turf surface with exposed roots. These shallow roots steal water and nutrients from turf. A root pruning program will be implemented to control root encroachment.
  • These fast growing softwood trees have begun to impact play due to size and improper placement. These overgrown trees now create “forced draws or fades”. Most impact is on tee shots. 
  • Unnecessary tree plantings of these fast growing coniferous trees have blocked beautiful vistas. These views are a very important design aspect of Stowe Country Club and they should not be lost to trees.
  • The thought that tree removal will make the course easier is untrue.  USGA Article